Dispute Adjudication Board
DAB / DAAB
Independent panel that makes immediately binding decisions on FIDIC disputes. Pay now, argue later. The 2017 edition upgraded the DAB to a standing DAAB with avoidance functions.
FIDIC Clause 20 / 21
Amicable Settlement
A 56-day mandatory attempt to settle before commencing FIDIC arbitration. A precondition to arbitration — not a formality. Failure to observe it may affect admissibility.
FIDIC Clause 20.5
Arbitration
Private adjudication producing a final, binding Award enforceable in 170+ countries. DIAC, ICC, and LCIA are the most commonly selected institutions for UAE construction disputes.
FIDIC Clause 20.6
Expert Witness
An independent specialist whose overriding duty is to the tribunal — not to the appointing party. Delay and quantum experts are most frequently appointed in UAE construction arbitrations.
Procedural / evidentiary role
Scott Schedule
A tabular document presenting disputed items side by side — claimant’s position, respondent’s position, tribunal determination. Standard in snagging disputes and final account proceedings.
Arbitration / litigation tool
Without Prejudice
WP
Protects genuine settlement communications from being used as evidence of liability. The label alone does not guarantee protection — the communication must be a genuine settlement attempt.
General legal principle
Loss and Expense
L&E
Financial loss arising from employer-risk matters that disrupted or prolonged the Works. JCT equivalent of FIDIC Cost + Profit. Each head of loss must be individually substantiated.
JCT / FIDIC Clause 20
Global Claim
A claim without direct causation links between specific events and specific losses. Strongly disfavoured by DIAC tribunals — frequently rejected in their entirety in UAE arbitrations.
Quantum methodology
Head Office Overheads
HOO
Central office costs attributable to a project — recoverable in prolongation claims. Hudson, Emden, or Eichleay formulae used. Must be substantiated by actual audited accounts.
FIDIC Cost — Clause 1.1.4.3
Adjudication
Rapid interim dispute resolution — binding immediately. No statutory adjudication in UAE (unlike UK). FIDIC DAB serves an equivalent function. DIAC’s expedited procedure takes ~45 days.
FIDIC DAB process