Finance Charges on FIDIC Claims | E-Basel

Basel Al Najjar

Basel Al Najjar is a UAE-based Civil Engineer, Expert Engineer, and Arbitrator specializing in construction law, contract management, and dispute resolution. With a strong professional background in engineering consultancy, Basel has developed advanced expertise in FIDIC contracts, UAE Civil Code applications in construction, and the preparation and evaluation of complex claims, including concurrent delay, disruption, and extension of time (EOT) matters. He advises contractors, consultants, and project stakeholders on contract strategy, risk mitigation, and dispute avoidance, combining technical engineering knowledge with legal and contractual insight. Basel’s work is driven by a practical, results-oriented approach aimed at resolving issues efficiently while safeguarding contractual rights and commercial interests. Through his publications, he provides clear, actionable insights to support professionals in managing construction risks, strengthening claims, and navigating disputes with confidence. For consultancy services, expert opinion, or arbitration-related matters, inquiries can be submitted through this website.

Expert Engineer | Arbitrator | Construction Law Specialist

FIDIC

Finance Charges on FIDIC Claims — Interest and Compound Costs

When employer-caused delay or non-payment forces a contractor to borrow or defer investment, the cost of that financing is recoverable as loss and expense. Yet it is routinely omitted from claims — leaving significant money on the table.

5 min read · Updated 23/05/2026

Basel Al Najjar — DIAC Arbitrator and Expert Witness

By Basel Al Najjar

Civil Engineering Consultant, DIAC Arbitrator, Tribunal Chairman and Accredited Expert Witness. Over two decades advising UAE contractors, developers and law firms on FIDIC, claims and arbitration.

Key takeaway

Finance charges on FIDIC claims are a recoverable head of loss under Clause 20.2. They must be calculated on a compound basis from the date each cost was incurred, supported by evidence of actual borrowing cost or a demonstrably reasonable opportunity cost rate. Omitting this head of loss significantly undervalues the claim.

1. Entitlement to Finance Charges Under FIDIC

FIDIC Red Book 2017, Clause 20.2 expressly includes “financing charges” in the contractor’s entitlement to direct loss and expense. This reflects the commercial reality that every pound spent in consequence of an employer-caused event has a financing cost: the contractor must fund that expenditure and bear the cost of the funds used.

The entitlement is grounded in contract law principle (Hadley v Baxendale): the cost of financing additional expenditure is a probable consequence of the employer’s breach and was within the reasonable contemplation of the parties at the time of contracting. A commercial contractor operating on any size of project must finance its operations — the cost of doing so is the employer’s liability if the employer causes the need for additional expenditure.

The financing charge accrues from the date the cost is incurred, not from the date it is certified or paid. A site supervision cost of AED 100,000 incurred in Month 3 (because of prolongation) has financing cost from Month 3 onwards, compounding until either the cost is recovered or the claim is settled.

2. Actual Borrowing Cost vs. Opportunity Cost

The rate at which financing charges should be calculated depends on how the contractor financed the additional expenditure. There are two scenarios:

Actual Borrowing: If the contractor arranged a bank facility or overdraft to finance the additional costs, the rate charged by the bank is the appropriate measure. The contractor should provide evidence: the facility letter showing the interest rate, bank statements showing charges, or a calculation from the contract between the contractor and the bank.

Opportunity Cost: If the contractor did not borrow but instead deferred investment or drew down cash reserves, the appropriate rate is the contractor’s opportunity cost — the rate the contractor could have earned on that cash if it had been invested. This is typically calculated by reference to the contractor’s cost of capital or a published benchmark (the Central Bank base rate plus a margin, or LIBOR/SOFR equivalent).

The contractor should use actual borrowing cost where available — it is more defensible and typically reflects the contractor’s true financial position. If actual borrowing is not available, a reasonable opportunity cost rate (typically 4–7% depending on market conditions and the contractor’s credit rating) is justifiable.

3. Calculation Methodology — Simple and Compound Interest

Finance charges should be calculated on a compound basis — reflecting the actual compounding of interest on borrowed funds. Simple interest (interest on the principal only, not on accumulated interest) understates the cost and should not be used.

The formula for compound interest is: A = P(1 + r/n)^(nt), where P is the principal, r is the annual rate, n is the compounding frequency (typically 12 for monthly), and t is the time period in years.

In practice, for construction claims, financing charges are typically calculated on a monthly basis, compounding monthly. Example: AED 1 million incurred in Month 1 on a project delayed by 12 months, at 5% annual interest compounded monthly:

Compound Interest Calculation

Month 1: AED 1,000,000 × 0.4167% = AED 4,167 interest; Month 2: (AED 1,000,000 + AED 4,167) × 0.4167% = AED 4,190 interest; and so on, compounding for 12 months. The total financing charge at 5% over 12 months is approximately AED 51,140, not AED 50,000 (which would be simple interest).

4. Documentation and Evidence

Finance charges should be documented from project inception. The contractor should maintain:

  • Bank facility letters or overdraft agreements setting out the interest rate and terms
  • Monthly bank statements showing interest charges
  • A calculation schedule showing financing charges accruing from the date each cost was incurred, monthly compounding
  • Documentation of the cost base (prolongation costs, cost of variations, additional preliminaries)

This documentation should be prepared contemporaneously — not reconstructed after the project ends. Monthly tracking of financing charges is the standard practice and is strongly preferred by arbitration tribunals.

5. Rate Justification

The rate applied should be defensible. If actual borrowing cost is used, the bank statements provide direct evidence. If opportunity cost is used, the contractor should justify the rate by reference to:

  • Published benchmark rates (Central Bank rate, SOFR, or equivalent) at the time the cost was incurred
  • The contractor’s own cost of capital (obtained from financial advisers or the contractor’s audited accounts)
  • Industry practice for rates applied in comparable claims

A rate that is grossly excessive (e.g., 20% when market rates are 5%) will be challenged. A rate that is defensibly supportable (5–7% in most environments) is unlikely to be significantly disputed.

6. Recovery in Arbitration

Finance charges are routinely recovered in FIDIC arbitration, particularly where the contractor presents clear evidence of actual borrowing cost or a justified opportunity cost rate. The fact that the contractor did not explicitly claim financing charges in its tender is irrelevant — it is part of the direct loss entitlement under Clause 20.2, not a separate contractual entitlement.

In settlement discussions, finance charges are often resolved by agreement — the parties agree a rate and a cost base, and the calculation follows mechanically. The cost of negotiating a dispute over financing charges (which is typically smaller than other claim elements) is rarely justified by either party, and agreement is common.

Are you omitting finance charges from your FIDIC claim?

On a AED 2 million prolongation claim over 24 months, finance charges at 5% compound can exceed AED 250,000. We advise on the calculation, documentation, and rate justification for finance charges in all types of FIDIC claims.

Book a 30-Minute Case Assessment →

Related reading

FIDIC

Prolongation Costs Under FIDIC Clause 20.2

The full cost base to which financing charges should be applied in delay claims.

FIDIC

FIDIC Clause 20.1 Notice Requirement

How to preserve finance charge entitlement through the notice procedure.

FIDIC

Loss and Expense Quantification Under FIDIC

The full range of recoverable costs and heads of loss available under Clause 20.2.

Calculating Finance Charges on Your FIDIC Claim

We advise on the calculation, documentation, and rate justification for financing charges. Applied properly, finance charges can significantly increase your claim value.

Book a 30-Minute Case Assessment →

Offices in Dubai · Available for instructions across the UAE and GCC

Disclaimer: This article constitutes general information for construction professionals. Finance charges must be calculated in accordance with the specific contract and project facts. Seek advice from a UAE-qualified legal practitioner before committing to any rate or calculation methodology for your specific claim.

Basel Al Najjar

Basel Al Najjar is a UAE-based Civil Engineer, Expert Engineer, and Arbitrator specializing in construction law, contract management, and dispute resolution. With a strong professional background in engineering consultancy, Basel has developed advanced expertise in FIDIC contracts, UAE Civil Code applications in construction, and the preparation and evaluation of complex claims, including concurrent delay, disruption, and extension of time (EOT) matters. He advises contractors, consultants, and project stakeholders on contract strategy, risk mitigation, and dispute avoidance, combining technical engineering knowledge with legal and contractual insight. Basel’s work is driven by a practical, results-oriented approach aimed at resolving issues efficiently while safeguarding contractual rights and commercial interests. Through his publications, he provides clear, actionable insights to support professionals in managing construction risks, strengthening claims, and navigating disputes with confidence. For consultancy services, expert opinion, or arbitration-related matters, inquiries can be submitted through this website.

Expert Engineer | Arbitrator | Construction Law Specialist

Permanent link to this article: https://www.e-basel.com/fidic/finance-charges-on-fidic-claims-e-basel/

Leave a Reply