Quantum Meruit Under FIDIC | E-Basel

Basel Al Najjar

Basel Al Najjar is a UAE-based Civil Engineer, Expert Engineer, and Arbitrator specializing in construction law, contract management, and dispute resolution. With a strong professional background in engineering consultancy, Basel has developed advanced expertise in FIDIC contracts, UAE Civil Code applications in construction, and the preparation and evaluation of complex claims, including concurrent delay, disruption, and extension of time (EOT) matters. He advises contractors, consultants, and project stakeholders on contract strategy, risk mitigation, and dispute avoidance, combining technical engineering knowledge with legal and contractual insight. Basel’s work is driven by a practical, results-oriented approach aimed at resolving issues efficiently while safeguarding contractual rights and commercial interests. Through his publications, he provides clear, actionable insights to support professionals in managing construction risks, strengthening claims, and navigating disputes with confidence. For consultancy services, expert opinion, or arbitration-related matters, inquiries can be submitted through this website.

Expert Engineer | Arbitrator | Construction Law Specialist

FIDIC

Quantum Meruit Under FIDIC — Recovery Where No Price Exists

Where a FIDIC contract is incomplete, ambiguous, or where work is performed outside the contract scope without an agreed price, quantum meruit may provide recovery — but on a fair value basis, not necessarily the contract price or the contractor’s tender rate.

5 min read · Updated 23/05/2026

Basel Al Najjar — DIAC Arbitrator and Expert Witness

By Basel Al Najjar

Civil Engineering Consultant, DIAC Arbitrator, Tribunal Chairman and Accredited Expert Witness. Over two decades advising UAE contractors, developers and law firms on FIDIC, claims and arbitration.

Key takeaway

Quantum meruit is a remedy of last resort — it arises where no enforceable contract exists for the work performed, and the employer has received and accepted the benefit of that work. Recovery is limited to a fair and reasonable price, not necessarily the contractor’s tender rate or full profit expectation.

1. When Quantum Meruit Arises in Construction

Quantum meruit (Latin: “as much as he has deserved”) arises in construction in several scenarios:

  • The parties agree in principle but no formal contract is executed; work begins under a letter of intent; and the formal contract is never finalised
  • The contractor performs work that is not covered by the contract scope — neither a variation nor a contractual obligation, but work requested by the employer and performed
  • An ambiguity or gap in the contract makes performance impossible under the agreed terms, and the contractor performs reasonably necessary work to accomplish the employer’s objective
  • The contract is void or unenforceable, but the contractor has performed work and the employer has benefited

In each case, the contractor has no contractual entitlement (because the contract does not cover the work or is non-existent), but the employer has received a benefit (the work is done and useful). Quantum meruit bridges this gap by requiring the employer to pay a fair price.

Quantum meruit is grounded in the law of restitution and unjust enrichment. The principle is that it is unjust for the employer to retain a benefit (the completed work) without paying for it.

The seminal case in construction is British Steel Corporation v Cleveland Bridge and Engineering Co Ltd [1984] 1 All ER 504. The contractor performed significant work under a letter of intent pending a formal contract that never materialised. The court held that the contractor was entitled to recover on a quantum meruit basis — payment for the work done at a fair and reasonable value — despite the absence of an enforceable contract.

However, the court also held that quantum meruit recovery is limited: it does not include loss of bargain (the difference between the contract price the contractor would have charged and the fair value actually recovered) or contractual remedies (damages for breach, penalty provisions, and so forth).

3. Conditions for Recovery

Three conditions must be satisfied for quantum meruit recovery:

The Defendant Was Enriched

The employer received a benefit — work was performed, materials delivered, or services rendered, and that work is now part of the completed project.

At the Claimant’s Expense

The contractor incurred the cost of that work — paying for labour, materials, supervision, and plant. The contractor bore the cost; the employer received the benefit.

It Would Be Unjust to Retain the Benefit Without Payment

It would be inequitable for the employer to have the benefit of the completed work without compensating the contractor for it. This is typically the case where the work was requested, accepted, and incorporated into the project.

4. Measurement of the Fair Value

The quantum meruit recovery is assessed as the “fair and reasonable value” of the work — not the contract price (because there is no valid contract), not the contractor’s tender rate (which may be inflated), and not necessarily what the contractor actually spent (which may be inefficient).

Fair value is typically assessed by reference to: (1) what reasonable contractors would have charged for similar work in similar circumstances; (2) industry rates and benchmarks; (3) cost-plus-reasonable-profit methodologies; and (4) expert evidence from quantity surveyors or construction cost specialists.

The court or tribunal will not award the full contract price (because the parties never agreed to that price). It will assess what a reasonable price would have been, absent an agreed contract. This may be higher or lower than the contractor’s tender, depending on the specific circumstances.

5. Limitations and Exclusions

Quantum meruit is not a path to unlimited recovery. Key limitations include:

  • No loss of bargain: The contractor cannot recover the profit it expected to earn under a contract price, only the fair value of the work done
  • No contractual remedies: The contractor cannot claim damages for breach, penalties, or other contractual consequences — only the fair value
  • No recovery for work the employer did not request or accept: If the contractor performed work gratuitously or without the employer’s knowledge or acceptance, quantum meruit is unavailable
  • No recovery where a contract exists but is unpriced: If there is an enforceable contract (even if prices are missing or ambiguous), the court will try to fill the gaps and enforce the contract, rather than resort to quantum meruit

6. Application Under FIDIC

Under FIDIC contracts, quantum meruit claims most commonly arise where variations are ordered but not valued, or where work is performed beyond the contract scope without a written variation instruction or agreed price.

FIDIC Clause 13 (Variations) contemplates that variations will be valued: either at contract rates, or if not available, at fair rates. This variation valuation mechanism is distinct from quantum meruit — it applies where there is a contract and a variation is ordered, but the price is unclear.

Quantum meruit arises more rarely under FIDIC — typically in circumstances where the contract is genuinely non-existent or void, or where work is performed with the engineer’s approval but entirely outside the contract scope and without any price mechanism.

The contractor’s best protection is to ensure that every variation is formally documented, valued, and approved by the engineer before work commences. Reliance on quantum meruit as a fallback is risky and rarely produces full recovery.

Work performed without a clear contract or price?

We advise on quantum meruit recovery, fair value assessment, and the constraints on restitution claims. This remedy is available but should be treated as a last resort, not a strategy.

Book a 30-Minute Case Assessment →

Related reading

FIDIC

Variations Under FIDIC Clause 13

The contractual mechanism for pricing work beyond the original scope — preferable to quantum meruit.

FIDIC

Letters of Intent — Binding Effect and Quantum Meruit

When letters of intent fail to become formal contracts and quantum meruit arises.

FIDIC

Contract Formation Under FIDIC

How FIDIC contracts are formed and what happens when formation is incomplete.

Quantum Meruit Assessment and Valuation

We advise on fair value assessment, restitution claims, and the limitations of quantum meruit recovery. This remedy is available but constrained — proper contract documentation remains the best protection.

Book a 30-Minute Case Assessment →

Offices in Dubai · Available for instructions across the UAE and GCC

Disclaimer: This article constitutes general information for construction professionals. It is not legal advice. Quantum meruit recovery depends on the specific factual circumstances, the applicable law, and the evidence available. Seek advice from a UAE-qualified legal practitioner before relying on quantum meruit as a recovery mechanism.

Basel Al Najjar

Basel Al Najjar is a UAE-based Civil Engineer, Expert Engineer, and Arbitrator specializing in construction law, contract management, and dispute resolution. With a strong professional background in engineering consultancy, Basel has developed advanced expertise in FIDIC contracts, UAE Civil Code applications in construction, and the preparation and evaluation of complex claims, including concurrent delay, disruption, and extension of time (EOT) matters. He advises contractors, consultants, and project stakeholders on contract strategy, risk mitigation, and dispute avoidance, combining technical engineering knowledge with legal and contractual insight. Basel’s work is driven by a practical, results-oriented approach aimed at resolving issues efficiently while safeguarding contractual rights and commercial interests. Through his publications, he provides clear, actionable insights to support professionals in managing construction risks, strengthening claims, and navigating disputes with confidence. For consultancy services, expert opinion, or arbitration-related matters, inquiries can be submitted through this website.

Expert Engineer | Arbitrator | Construction Law Specialist

Permanent link to this article: https://www.e-basel.com/fidic/quantum-meruit-under-fidic-e-basel/

Leave a Reply