Return to Articles

Interest and Damages

Interest and Damages.

Damages in Construction Claim | Interest 

Interest and Damages.

Interest and Damages.

Interest is either interest as a component of the claim, or interest after the award.

Each is for different period of time. the rates may also different.

Interest can be a very substantial component of the claim. Sometimes, by the time the claim comes to trail, interest will be the largest component of the claim. It is always important to claim interest as a component of the claim.

Usually, if interest is not claimed as a component of the claim, a court, tribunal, arbitrator or adjudicator cannot include interest in the amount which the court, tribunal, arbitrator or adjudicator awards to the claimant.

if interest is claimed then, provided the claimant is successful, an amount of interest calculated up to the date of the award should be included in the amount awarded.

the claimant should include in the statement of claim a claim for such interest.

When claiming interest as a component as a component of claim, it is important to select the appropriate category of interest. Interest may be able to be claimed:

1- Under a provision in the contract.

2- Under a provision of an agreement for arbitration or expert determination.

3- Under statute, or as a damages.

as a component of claim, the claimant will usually only be entitled to one of the categories of interest.

Usually, interest after the award applies automatically to the amount of the award and does not have to be claimed.

The power of an arbitrator to award interest may be found in the arbitration agreement, and the arbitrator may include in the award interest on the whole or any part for the period between the date when the cause of action arose and the date on which the award made.

Interest Under the Construction Contract.

Most standard forms of construction contract contain a provision for interest on late payments.

If any moneys due to either party remain unpaid after the date upon which or the expiration of the period within which they should have been paid then interest shall be payable thereon from but excluding the date upon which or the expiration of the period within which they should have been paid to and including the date upon which the moneys are paid.

when the contract provides for rate of interest and the claimant claims interest at that rate, the court, arbitrator or adjudicator should give effect to the agreed rate unless there is a statutory minimum rate and the rate in the contract is less than the statutory minimum rate.

Interest Under an Agreement for Arbitration or Expert determination.

It is always open to the parties to an arbitration agreement to endow the arbitration with a greater or less power to award interest than exists in the applicable commercial arbitration act.

In expert determination, the power, if any, of the expert to include interest in the amount determined depends upon the terms of the agreement for expert determination.

When drafting an expert determination agreement it is important to consider this point.

Example: 

Interest under an agreement for arbitration or expert determination refers to the compensation or amount payable to a party for the delay in payment of a sum that is subject to arbitration or expert determination.

The interest can be calculated based on the agreement between the parties, the governing law, or any applicable rules. The formula for calculating interest may differ depending on the jurisdiction and the specific terms of the agreement, but generally, it is calculated as a percentage of the principal amount owed.

One common formula for calculating interest is:

I = P × R × T

Where: I = interest P = principal amount R = interest rate T = time period

For example, if the principal amount is $10,000, the interest rate is 5% per annum, and the time period is 6 months, the interest would be:

I = 10,000 × 0.05 × (6/12) I = $250

Alternatively, interest can be calculated using a compounding formula, which takes into account the accumulated interest over time. The formula for calculating compounded interest is:

A = P × (1 + r/n)^(n × t)

Where: A = total amount payable (principal plus interest) P = principal amount r = annual interest rate n = number of times interest is compounded per year t = time period

For example, if the principal amount is $10,000, the annual interest rate is 5%, and interest is compounded monthly, the interest payable after 6 months would be:

n = 12 (compounded monthly) t = 6/12 (6 months) r = 0.05

A = 10,000 × (1 + 0.05/12)^(12 × 6/12) A = $10,256.81

In addition to the interest rate, parties may also agree on a specific date from which interest accrues and a compounding frequency, if any.

In summary, interest under an agreement for arbitration or expert determination is the compensation payable for delayed payment of a sum subject to arbitration or expert determination. It can be calculated using different formulas, such as simple interest or compounded interest, depending on the governing law or agreement between the parties.

Damages

Damages are the general remedy available for all kinds of breaches of contract. If monetary obligations are not performed, interest may be added as an additional remedy that does not exclude the simultaneous awarding of damages.

The Importance of Understanding Damages in Construction Claims

Construction projects are complex and involve a variety of parties, including owners, contractors, subcontractors, suppliers, and consultants. With so many different parties involved, disputes are bound to arise. When a dispute cannot be resolved amicably, one or more parties may file a claim or initiate legal action.

In construction claims, damages are the monetary compensation sought by a party for losses incurred as a result of another party’s actions or inactions. Damages can be categorized into two types: direct and indirect. Direct damages are those that flow directly from the breach of contract or other wrongful act, while indirect damages are those that are not a direct result of the breach but arise as a consequence of it.

Direct Damages in Construction Claims

Direct damages in construction claims are often referred to as “actual damages” or “compensatory damages.” These damages are intended to compensate the injured party for losses incurred as a result of the other party’s actions or inactions. Direct damages can include, but are not limited to, the following:

  1. Cost of Repair or Replacement

If the contractor or subcontractor fails to complete the work as specified in the contract or performs defective work, the owner may have to pay another contractor to repair or replace the defective work.

  1. Delay Damages

If the project is delayed due to the contractor’s or subcontractor’s actions or inactions, the owner may be entitled to damages to compensate for the increased costs associated with the delay.

  1. Loss of Income or Use

If the owner is unable to use the property as intended due to the contractor’s or subcontractor’s actions or inactions, the owner may be entitled to damages to compensate for the loss of income or use.

Indirect Damages in Construction Claims

Indirect damages in construction claims are often referred to as “consequential damages.” These damages are not a direct result of the breach of contract or other wrongful act but arise as a consequence of it. Indirect damages can include, but are not limited to, the following:

  1. Lost Profits

If the owner is unable to use the property as intended due to the contractor’s or subcontractor’s actions or inactions, the owner may be entitled to damages to compensate for lost profits.

  1. Increased Costs

If the project is delayed due to the contractor’s or subcontractor’s actions or inactions, the owner may be entitled to damages to compensate for the increased costs associated with the delay.

  1. Damage to Reputation

If the contractor’s or subcontractor’s actions or inactions result in damage to the owner’s reputation, the owner may be entitled to damages to compensate for the loss of reputation.

Conclusion

In conclusion, understanding damages in construction claims is essential for all parties involved in a construction project. Direct damages are intended to compensate the injured party for losses incurred as a result of the other party’s actions or inactions. Indirect damages are not a direct result of the breach of contract or other wrongful act but arise as a consequence of it. By understanding the types of damages that can be sought in a construction claim, parties can better protect themselves and their interests in the event of a dispute.

 

 

 

 

 

 

 

 

Permanent link to this article: http://www.e-basel.com/articles/interest-damages/