Basel Al Najjar is a UAE-based Civil Engineer, Expert Engineer, and Arbitrator specializing in construction law, contract management, and dispute resolution. With a strong professional background in engineering consultancy, Basel has developed advanced expertise in FIDIC contracts, UAE Civil Code applications in construction, and the preparation and evaluation of complex claims, including concurrent delay, disruption, and extension of time (EOT) matters. He advises contractors, consultants, and project stakeholders on contract strategy, risk mitigation, and dispute avoidance, combining technical engineering knowledge with legal and contractual insight. Basel’s work is driven by a practical, results-oriented approach aimed at resolving issues efficiently while safeguarding contractual rights and commercial interests. Through his publications, he provides clear, actionable insights to support professionals in managing construction risks, strengthening claims, and navigating disputes with confidence. For consultancy services, expert opinion, or arbitration-related matters, inquiries can be submitted through this website.

Expert Engineer | Arbitrator | Construction Law Specialist



Contract » Contract Formation

Contract Formation by Conduct — When Behaviour Binds

Works commence, invoices are paid, months pass — and then a dispute reveals that no one ever signed the contract. This is how behaviour-based contracts are formed on UAE sites, and why they are among the most dangerous instruments in construction procurement.

5 min read · Updated 21/04/2026

Basel Al Najjar — DIAC Arbitrator and Expert Witness

By Basel Al Najjar

Civil Engineering Consultant, DIAC Arbitrator, Tribunal Chairman and Accredited Expert Witness. Over two decades advising UAE contractors, developers and law firms on FIDIC, claims and arbitration.

Key takeaway

The absence of a signed contract does not mean there is no contract. Courts will objectively assess the parties’ conduct to determine whether a contract has been formed — and will then determine its terms by reference to the last un-rejected document in the pre-contract exchange. The party whose terms are incorporated has a significant advantage. The cost of delay in contract execution rarely exceeds the cost of a dispute about what was agreed.

1. Why conduct-based contracts arise on UAE sites

In UAE construction procurement, the gap between commercial agreement and formal execution is frequently filled by activity. Contractors mobilise and start on site. Employers receive work, inspect it, and certify payment applications. Invoices are submitted and partly paid. Months pass. Then something goes wrong — a variation dispute, a delay claim, a payment shortfall — and both parties discover that no one ever signed the formal agreement.

The absence of a signed contract does not mean there is no contract. Both common law systems and the UAE Federal Civil Transactions Law recognise that a binding contract can be formed by the conduct of the parties. The difficulty is that conduct-based contracts are inherently uncertain as to their terms, which makes them fertile ground for dispute about what was actually agreed.

The common scenarios in UAE practice include: works commence before all commercial terms are finalised; the contractor starts on site following a letter of award without waiting for the formal contract to be returned countersigned; or a verbal instruction to proceed is given and acted upon. In each case, a tribunal examining the dispute will ask three questions: did the parties intend to contract, did they reach agreement on the essential terms, and was there consideration?

The foundational principle is that courts and tribunals will objectively assess whether a reasonable person, observing the parties’ conduct, would conclude that a contract had been formed. Subjective belief is not determinative — what matters is the outward behaviour of the parties judged against the factual background.

Leading authority

In G Percy Trentham Ltd v Archital Luxfer [1993] 1 Lloyd’s Rep 25, the Court of Appeal confirmed that a contract can crystallise during the performance of the works, even where not all terms were agreed at the outset. The performance itself becomes evidence of the contractual intention.

Once a contract is found to have been formed by conduct, the tribunal must then determine its terms. This is typically done by reference to the last document in the pre-contract exchange that was not expressly rejected — often the employer’s letter of award, the purchase order, or the contractor’s tender. The party whose terms are incorporated by this mechanism may hold a significant procedural and commercial advantage when the dispute is framed.

3. Practical application for contractors and employers

For contractors

Never commence works without at minimum a signed letter of intent identifying the contract terms that will govern. If the formal contract has not been executed, write to the employer identifying the terms on which you are proceeding and inviting confirmation. Do not assume that your tender conditions or standard terms are incorporated simply because you submitted them — the employer’s award letter may incorporate its own terms by reference, and that reference may prevail.

For employers

Issue formal contracts promptly after award. Do not allow contractors to commence on site without at minimum a countersigned letter of intent. Ensure that any pre-contract communications expressly reference the contract terms that are to apply, and that no subsequent contractor correspondence has sought to substitute different terms without rejection.

Working on site without a signed contract?

If you are in dispute over the terms of an unsigned or partially executed contract, we can assess your exposure and advise on the best route to a defensible position. Our team acts for contractors, developers and employers across the UAE.

Book a 30-Minute Case Assessment →

4. The risks cut both ways

The exposure created by a conduct-based contract is asymmetric but material for both parties.

For the contractor: the absence of formal contract terms means the loss of carefully negotiated protections. Limitation of liability caps, dispute resolution procedures, notice periods, payment terms, and retention provisions may all be absent — or replaced by unfavourable implied terms that the contractor never accepted.

For the employer: an implied contract may not include liquidated damages provisions. Without LDs, the employer’s remedy for delay is general damages — which must be proved — and in more serious cases the contractor may argue that time is at large, meaning the obligation is only to complete within a reasonable time. That outcome can be commercially catastrophic for a development with funding milestones.

5. Mitigation — protecting your position

The single most effective mitigation is to execute the formal contract before works commence. Where this is not possible, a well-drafted letter of intent that incorporates the contract terms by reference, and is signed by both parties, provides a workable alternative. See our related article on letters of intent for detailed drafting guidance.

  • Maintain a contract execution register to track the status of every contract in the programme.
  • Write formally when proceeding at risk — identify the terms on which works are continuing and invite confirmation.
  • Escalate through project management channels when execution is repeatedly delayed beyond 30 days.
  • Ensure that anyone authorised to start works has been briefed on contract status before mobilisation.

6. Conclusion

Contracts formed by conduct are an avoidable problem. The pressure to start works quickly is real, particularly on fast-track UAE developments with funding or handover deadlines. But the risk of starting without a formal agreement in place is greater than the delay caused by waiting. The cost of delay in contract execution rarely exceeds the cost of a dispute about what was or was not agreed — or a tribunal finding that turns on whose purchase order happened to be the last document sent before the concrete was poured.

Related reading

Contract

Letters of Intent — Binding Effect and Legal Exposure

How letters of intent expose UAE employers and contractors to open-ended liability, and how to draft them defensively.

Contract

Battle of the Forms — Whose Terms Govern?

The last-shot doctrine and how competing standard forms resolve into a binding contract — often to one party’s surprise.

Contract

Entire Agreement Clauses — The Limits of Prior Negotiations

Why entire agreement clauses do not automatically exclude misrepresentation claims in UAE construction.

Is your contract properly formed?

We advise UAE contractors, developers and law firms on contract formation disputes, conduct-based contracts, and the preservation of claims where no signed agreement exists. Early review often prevents what becomes a substantial arbitration.

Book a 30-Minute Case Assessment →

Offices in Dubai · Available for instructions across the UAE and GCC

Basel Al Najjar

Basel Al Najjar is a UAE-based Civil Engineer, Expert Engineer, and Arbitrator specializing in construction law, contract management, and dispute resolution. With a strong professional background in engineering consultancy, Basel has developed advanced expertise in FIDIC contracts, UAE Civil Code applications in construction, and the preparation and evaluation of complex claims, including concurrent delay, disruption, and extension of time (EOT) matters. He advises contractors, consultants, and project stakeholders on contract strategy, risk mitigation, and dispute avoidance, combining technical engineering knowledge with legal and contractual insight. Basel’s work is driven by a practical, results-oriented approach aimed at resolving issues efficiently while safeguarding contractual rights and commercial interests. Through his publications, he provides clear, actionable insights to support professionals in managing construction risks, strengthening claims, and navigating disputes with confidence. For consultancy services, expert opinion, or arbitration-related matters, inquiries can be submitted through this website.

Expert Engineer | Arbitrator | Construction Law Specialist

Permanent link to this article: https://www.e-basel.com/fidic/contract-formation-by-conduct-in-uae/

Leave a Reply