Return to Contractual

How to Deal with Provisional Sums Under FIDIC 1999

How to Deal with Provisional Sums Under FIDIC 1999: A Guide for UAE Construction Professionals

How to Effectively Manage Provisional Sums in FIDIC 1999 Contracts

Introduction

Did you know that provisional sums are often the source of significant misunderstandings and disputes in construction contracts? In the UAE, where construction projects are often ambitious and complex, navigating provisional sums in contracts governed by FIDIC 1999 requires expertise and attention to detail. These sums, intended to provide flexibility for undefined works, can become a stumbling block if not managed effectively.

But what exactly are provisional sums, and why are they critical in ensuring smooth project execution? Whether you’re a contractor, consultant, or employer, understanding the nuances of provisional sums is essential for successful contract administration. This article delves into the intricacies of provisional sums under FIDIC 1999, offering practical insights and actionable strategies for managing them effectively.

How to Deal with Provisional Sums Under FIDIC 1999: A Guide for UAE Construction Professionals

How to Deal with Provisional Sums Under FIDIC 1999: A Guide for UAE Construction Professionals

Understanding Provisional Sums Under FIDIC 1999

What Are Provisional Sums?

Provisional sums are pre-allocated amounts in a construction contract set aside for work that is undefined at the time of signing. These sums allow for future decisions regarding specific work items or materials, offering a level of flexibility to the employer or engineer.

Why Are Provisional Sums Important?

In the dynamic construction landscape of the UAE, provisional sums serve as a safety net for unexpected changes or additional requirements. However, they also come with challenges, including potential disputes over scope, costs, and timing.

The Role of FIDIC 1999 in Managing Provisional Sums

The FIDIC 1999 Red Book provides a structured approach to handling provisional sums. Key clauses, such as Clause 13 (Variations and Adjustments) and Clause 8.4 (Extension of Time), outline the rights and obligations of all parties involved. However, interpreting these clauses correctly is critical to avoid misunderstandings.

Best Practices for Managing Provisional Sums

Defining the Scope of Work

Clearly defining the scope of work associated with provisional sums is paramount. A well-defined scope ensures:

  • All parties understand what the provisional sum covers.
  • Reduced disputes over additional instructions or variations.
  • A clear basis for cost adjustments and payments.

For instance, if a provisional sum is allocated for a cladding package, it must specify whether it includes design, supply, and installation or just one of these elements.

Timely Instructions and Communication

Provisional sums require precise and timely instructions from the employer or engineer. Key considerations include:

  • Timing: Delayed instructions can disrupt the project schedule, impacting the critical path.
  • Documentation: Contractors should document all delays and assess their impact, potentially claiming an extension of time if justified.

For example, if an instruction to execute work under a provisional sum is issued late, the contractor must evaluate its impact on critical activities and seek appropriate relief under the contract.

Adhering to Contractual Limits

The FIDIC 1999 contract mandates that provisional sums must be used “in whole or in part” but not exceed the specified amount unless all parties agree. Contractors should ensure:

  • Compliance with the contractual provisions.
  • Clear records of costs incurred.
  • Transparent communication with the employer and engineer regarding any adjustments.

Sufficiency of the Accepted Contract Amount

Clause 4.11 of the FIDIC 1999 contract emphasizes that the accepted contract amount covers all contractor obligations, including those related to provisional sums. This implies that contractors must account for programming risks associated with provisional sums unless otherwise stated in the contract.

Case Examples of Provisional Sums in Action

Case 1: Provisional Sum Included in the Contract

If a cladding package is listed as a provisional sum, the contractor is entitled to:

  • Payment for the actual cost of subcontract work.
  • An overhead and profit percentage as specified in the Bill of Quantities (BOQ) or Appendix to Tender.

For example, a contractor incurs AED 500,000 for a subcontracted cladding package. With an agreed overhead and profit percentage of 10%, the contractor would receive AED 550,000 in total.

Case 2: No Provisional Sum Listed

If a landscape package is not listed as a provisional sum but is instructed later, the contractor may treat it as additional work. In this case:

  • Overhead and profit percentages in the Appendix to Tender would apply.
  • An extension of time might be claimed if the work impacts critical path activities.

For instance, if the landscape work delays project completion by 15 days, the contractor can seek an extension based on the delay’s impact on the critical path.

Challenges and Ambiguities in Provisional Sums

Ambiguity in Extension of Time Entitlements

The FIDIC 1999 Red Book does not explicitly mention provisional sums as grounds for an extension of time under Clause 8.4. This creates uncertainty regarding whether contractors assume programming risks for such sums. However, Clause 4.11 suggests that all contractor obligations, including those under provisional sums, are covered within the accepted contract amount.

Practical Considerations in the UAE Context

In the UAE, the interpretation of these clauses often depends on the specific contract terms and project circumstances. Contractors must ensure meticulous record-keeping and proactive communication to safeguard their interests.

Frequently Asked Questions (FAQs)

  1. What is a provisional sum in FIDIC 1999?
    A pre-allocated amount in the contract for undefined work at the time of signing.
  2. Can a contractor claim an extension of time for provisional sum works?
    It depends on the impact of the work on the critical path and the contract terms.
  3. How are provisional sums adjusted?
    Based on actual costs incurred, plus overhead and profit percentages specified in the contract.
  4. Who decides how provisional sums are spent?
    The employer or engineer issues instructions regarding the use of provisional sums.
  5. What happens if a provisional sum is not fully utilized?
    Only the actual costs incurred are paid, and unused amounts remain with the employer.

Conclusion

Provisional sums are an integral part of construction contracts governed by FIDIC 1999, offering flexibility for undefined works. However, their effective management requires a thorough understanding of contractual obligations, proactive communication, and meticulous record-keeping.

By clearly defining the scope, adhering to contractual limits, and addressing timing and cost implications, contractors can navigate provisional sums confidently, safeguarding their interests and ensuring smooth project execution.

As the UAE continues to witness rapid development, mastering the art of managing provisional sums will remain a critical skill for construction professionals.

 

#ConstructionUAE, #FIDICContracts, #ProjectManagement, #UAEDevelopment, #ConstructionLaw, #EngineeringConsulting, #ContractAdministration, #ProvisionalSums, #ConstructionClaims, #ConstructionManagement, #ContractorTips, #UAEProjects, #ConstructionBestPractices, #CriticalPath

Permanent link to this article: https://www.e-basel.com/contractual/how-to-deal-with-provisional-sums-under-fidic-1999/